66 inside stiffened, Starting location of ladders, Ladder safety cage, and platform instructions – Grain Systems Bin Accessories PNEG-1096 User Manual

Page 11

Advertising
background image

11

PNEG-1096 Ladder, Safety Cage, & Platforms

2.66 INSIDE STIFFENED

All packages have been structured with the correct components for each ring height grain

bin from 6 rings to 37 rings. Be sure and follow the complete instruction sheets for correct
placement of parts. Failure to do so may result in improper fit of parts or shortage of parts. Read
through the complete set of instructions before proceeding with erection of grain bin.
Considerable thought must be given as to location of ladders and platforms in relation to other
equipment and structures.

STARTING LOCATION OF LADDERS

Ladder placement is very critical as to assure proper fit of all parts later on as safety cage is
bolted in place. Locate the proper place for the roof ladder and manway this will establish the
location of the ladder. Ladder must be centered directly below the roof ladder. Refer to the dia-
gram below for proper location of field drilled holes (3/8"). Holes must be 18 3/4" apart and 8"
below the top horizontal row of holes directly in line with the holes to be used for the platform
mounting angle. Platform must be located 9 3/8" to the right of the ladder holes. All of these
dimensions are very critical to assure proper fit of all parts!

LADDER SAFETY CAGE, AND PLATFORM INSTRUCTIONS

REV. 9/12/-00

HOLES FOR PLATFORM

18 3/4"

18 3/4"

9 3/8"

MANWAY PANEL

ROOF LADDER

FIELD DRILL
3/8" HOLES (2)

Advertising