5. Installation

PNEG-914 Flex-Flo

19

Straight-Through Tandem Installation

The straight-through tandem system should be installed the same as a single tank system with the
following exceptions:

1. Mount the boots on both tanks and the single or twin-out unloader as instructed.

2. Install baffle plate (FLX-4310) in the single-through unloader as shown in

Figure 5H

. The twin

unloader baffle is factory installed as shown in

Figure 5H

.

Figure 5H

3. Slide the belled end of a straight tube onto the unloader outlet on the first tank. Hold the straight

tubing in the desired mounting position. Mark and cut the straight tube at the point where the tube
and the inlet of the straight-through unloader inlet intersect.

4. Slip the appropriate tube coupler over the cut end of the straight tube. Position the straight tube in its

operating location. Slide and clamp the tube coupler over the straight-through unloader inlet.

(See Figure 5I.)

NOTE: The coupler should be equally distributed between the tubing and the unloader inlet.

Figure 5I Tandem System Installation

5. Feed the auger through the single/twin-out unloader to the rest of the system and anchor as instructed.