5. INSTALLATION
Upper Cable Guide Assembly
Once the location of the upper cable guide assembly is determined it must be fastened to the
trunking. The assembly of the clamp band and upper cable guide assembly (DFB0388) is shown
in the
. The 1/2" x 2" bolts and nuts that fasten the clamp bands to the
upper cable guide assembly are provide in the hardware package (FC-DCG-HDW). These
clamp bands vary depending on what size leg you have. Refer to the
clamp bands should be used.
Note: Use caution when tightening hardware, DO NOT overtighten and collapse trunking.
Figure 5D Trunking Removed for Clarity
Figure 5E Trunking Removed for Clarity
Pulley Dia.
Clamp Band
Qty
10"
GSB10174
2
16", 24", 30" & 36" Pulleys
Part #
Qty
Clamp Band
DSP16002
2
Clamp w/Rod Weldment
DSP16005
1