4. Dryer Installation

PNEG-1707 TM-Series Tower Dryer

19

Fuel System Requirements

Electrical Power Supply

An adequate power supply and proper wiring are important factors for maximum performance and long
life of the dryer. Electrical service must be adequate enough to prevent low voltage damage to motors
and control circuits. (See electrical requirements

on Page 20

.)

Transformers and Wiring Voltage Drop

Advise the service representative of the local power supplier that an additional load will be placed on the
line. Check on KVA rating of transformers, considering total horsepower load. The power supply wiring,
main switch equipment and transformers must provide adequate motor starting and operating voltage.
Voltage drop during motor starting should not exceed 14% of normal voltage, and after motor is running
at full speed it should be within 8% of normal voltage.

TM-1008

TM-1010

TM-1012

TM-1015

Liquid

Propane

Burner Capacity (Btu/hr)

1

8,200,000

9,700,000

11,200,000

14,300,000

Maximum Fuel Usage (gal/hr)

90

106

122

156

Recommended Liquid Line Size (<100')

3/4"

3/4"

3/4"

3/4"

Fuel Train Orifice Size (inch)

0.500"

0.625"

0.625"

0.7187"

Pressure Regulator Setting (lb/in

2

)

9

9

9

9

Natural

Gas

Burner Capacity (Btu/hr)

1

8,200,000

9,700,000

11,200,000

14,300,000

Maximum Fuel Usage (ft

3

/hr)

8200

9700

11200

14300

Recommended Fuel Line Size (<100')

2"

2"

2"

2-1/2"

Fuel Train Orifice Size (inch)

0.625"

0.688"

0.688"

0.8125"

Supplied Pressure to Fuel Train (lb/in

2

)

10

10

10

10

1

Burner capacity for fuel line sizing. Actual average fuel usage is typically 50%-60% of the burner capacity.