2. Installation

38

PNEG-1112 Sidewall Bin Stair Assembly

Handrail Installation

After all the stair sections have been assembled and installed, the upper and lower handrails can be
installed. The handrails can be installed top down, or bottom up.

The handrails have a smaller diameter at their upper ends, and have a pre-drilled hole at the lower end
to aid installation.

NOTE: The lengths of handrails that are provided correspond to the differing stair section lengths.

Assemble the correct handrails to the appropriate stair sections.

Figure 2AT

Lower Handrail Installation

1. Using the appropriate length of handrail, use one (1) 1/4'' x 1'' self drilling screw to attach the lower

end of the handrail to the inside surface of the lowest handrail baluster. The head of the screw
should be on the outside surface of the handrail baluster.

Figure 2AU