2. Installation
PNEG-1112 Sidewall Bin Stair Assembly
41
NOTE: In the same way that the lower handrails had to be curved/bent to match the curve of the bin, the
upper handrails have to be adjusted to match.
2. With the next appropriate length handrail, overlap the to-be-installed handrail to the previously
installed handrail. The two (2) handrails should overlap by at least 2''.
3. Where the installed handrail(s) meet up with the next higher handrail baluster, use one (1)
1/4'' x 1'' self drilling screw to attach the handrail to the outside surface of the handrail baluster. The
head of the screw should be on the inside surface of the handrail baluster.
Figure 2AZ
4. Repeat
until the handrail reaches the 51-1/2'' right platform post.
5. Where the assembled lower handrail meets the 51-1/2'' right platform post, use one (1) 1/4'' x 1''
self drilling screw to attach it to the outside surface of the post. The head of the screw should be
on the inside surface of the 51-1/2'' right platform post.
Figure 2BA