2. Installation

PNEG-1112 Sidewall Bin Stair Assembly

9

3. Consult

Figure 2B on Page 10

through

Figure 2G on Page 15

for the layout of the attachment

points, and where you will have to field drill.

4. Line up the correct hole in the platform wall bracket with the first horizontal seam bolt row. The

correct hole is indicated in the detail view of the corresponding layout figure. Knee braces should
be installed at the same time as the platform wall brackets.

5. Mark the location of the holes to be field drilled for the platform wall brackets, stair wall brackets

and knee braces, as shown by the corresponding layout figure.

NOTE: All stair wall brackets should line up with a hole in the horizontal seam bolt rows, except for a

platform being installed 26-1/2'' below the eave on a 44'' bin sheet. Using the center hole on the
stair wall bracket, place it approximately two (2) bolts over and one (1) hole down from the
platform wall bracket attachment point to the first horizontal seam bolt row.

Drilling and Installation

1. Using the marked holes from the previous

Steps

, field drill the mounting locations as indicated in

the corresponding layout figure. Use an 11/32'' steel drill bit to make the holes.

2. Mount the platform wall brackets, stair wall brackets, and the knee braces with the provided

5/16'' x 1-1/4'' bin bolts and serrated flange nuts. The highest two (2) knee braces need to be the
42-1/2'' knee braces, instead of 34-3/4'' knee braces that may be part of the package.

3. At the bottom of the bin, the final wall bracket and knee brace will be installed with the final

stair section.

4. One (1) bolt spacing is the distance between the bolts on the horizontal seams, which is

equal to 9-3/8".

5. For 32" bin sheets: Each stair wall bracket after the first bracket will be located three (3) bolt spaces

over (28-1/2") and one (1) horizontal seam down.

6. For 44" bin sheets: Each stair wall bracket after the first bracket (second bracket for 26-1/2" below

eave) will be located four (4) bolt spaces over (28-1/2") and one (1) horizontal seam down.