GE Industrial Solutions ASTAT BP User Manual

Page 54

Advertising
background image

ASTAT BP User Manual

54

GE Industrial Solutions

©2013 GE Company All Rights Reserved

66..22..33..11

Special Starting – Using DUAL Settings – Wiring Diagram

6.2.4

Choosing a Suitable Pump Curve (Centrifugal Pumps)

66..22..44..11

Starting Curve

Adjust Main Settings as necessary (Starter Current, Motor Current, etc.).

Set

Soft Starting Curve, Ramp UP Time, Current Limit, and Starting Voltage to their

default values (curve 0, 10 sec., 400% and 30% respectively).

Start the pump while watching the pressure gauge as the pump starts and look for overshooting (“pressure

surge”) of the gauge needle above the target pressure. In case of over pressure, choose a peak torque

reduction curve (Soft Start Curve 1!!).

Set

Soft Start Curve 1!!, increase Ramp UP Time to 15 seconds and reduce Current Limit to

350%. Start the pump and watch the pressure gauge while the pump starts.

In most cases overshooting is reduced. If the overshoot persists, increase

Ramp UP Time to 25 seconds

(confirm with the motor manufacturer) and try again.

If overpressure persists, increase the

Soft Start Curve setting to 2!! or 3!! if necessary. Each

increase in the

Soft Start Curve setting will reduce the peak torque, thus reducing the overpressure

and preventing “pressure surge” during start.