3-1
3. Installation
031-093-C0-001 © 3/99
The following procedure will allow for installation of the Collocated CE-G with
the CE-X/ CE-X2. The CE-G enclosure re is bolted to the concrete pad using
7/16 bolts and to the CE-X APU enclosure by carriage bolts. Also this
procedure will explain step by step how to install the two 40 LB propane tanks
and the regulator /control valve.
Tools:
(2) Pipe wrench 10
7/8 combination box and open ended wrench
Straight slot screw driver
Multimeter
Adjustable crescent wrench 10
1/2 open ended wrench
Materials
QTY
(1)
Regulator hold down bracket assembly
(2)
40 pound DOT approved propane tanks
(1)
CE-G Enclosure
3.1Tools and Materials