DTG 130 Eco.NOx

01/02/11 - 300002915-001-E

4.3 Mounting

4.3.1

Position of the boiler

Installations possible:
- in the kitchen
- in the cellar
- in the boiler house

Clearance to allow for:
- 5 cm on one of the boiler sides (B)
- 70 cm minimum in front
- 5 at the rear (A)

Also have the required space for installing the expansion reservoir
and the heating circulator.

4.3.2

Ventilation



Do not obstruct the air inlets in the room (even partially).

France: the cross section of the aeration vent, which is compulsory
in the boiler room in which the boiler is installed, must comply with the
DTU 61.1 (P 45 204) standard and, in particular, with the instruction
on boiler room layout (Book 1764 April 1982).
Germany: the cross section of the ventiliation vents, which are
compulsory in the room in which the boiler is installed, must comply
with the VDI 2050 form 1 standard and with other prevailing
regulations.
Other countries: the cross section of the aeration inlet, which is
compulsory in the premises in which the boiler is installed, must
comply with the standards in force in the country.



Caution:

In order to avoid damage to the boiler, it is necessary to prevent the
contamination of combustion air by chlorine and/or fluoride
compounds, which are particularly corrosive. These compounds are
present, for example, in aerosol sprays, paints, solvents, cleaning
products, washing products, detergents, glues, snow clearing salts,
etc. Therefore:

- Do not pull in air evacuated from premises using such products:

hairdressing salons, dry cleaners, industrial premises (solvents),
premises containing refrigeration systems (risk of refrigerant
leakage), etc.

- Do not stock such products close to the boilers.

If the boiler and/or peripheral equipment are corroded by such
chloride or fluoride compounds, the contractual guarantee
cannot be applied.