Fz-4s set-up – Diamond Products FZ-4S User Manual

Page 21

Advertising
background image

FZ-4S

Set-up

FZ-4S_e_0205.fm

Page 21

3URFHGXUH

z

Mark cutting line on the concrete

z

Mark dowel line at a distance of 22 cm.

(The same distance applies for flush cuts)

z

Drill dowel hole and fit dowel according to
dowel manufacturer’s instructions

z

Mount V-rail supports (9) on V-rails (1).

z

Mount rail unit on concrete and align using
cut guide (10)

z

Align rail unit with adjusting foot (8), so that
all adjusting feet (8) and the adjusting
screws (4) are supported by the concrete.

z

Tighten rail unit (1)

5DLO OLPLW VWRS

z

Mount rail limit stop on the end of the rail, so
that the wall saw head cannot fall off the
rail.

Clearance between rail supports:

- where a single rail is used, as high as possible

- where a number of rails are used, evenly distributed

along the entire length of rail.

Once rail unit has been mounted
check adjusting nut (3) and
clamping block (6) anchoring