SECTION 2

FTA-IOM-2013-0227

INSTALLATION

2-15

!

WARNING

All information in this manual is for
reference and guidance purposes,
and does not substitute for required
professional training, conduct,
and strict adherence to applicable
jurisdictional/professional codes and
regulations.

4

CAUTION

The weight of all piping must be
properly supported. Failure to support
piping may result in equipment
damage and/or system leakage.

Piping must take into consideration
potential for damage as a result of
expansion, contraction, vibration, or
other movements.

Dirt, water, and/or other debris in the
piping system after welding may result
in equipment failure.

suitable for the aggregate head, against a closed valve, of both pumps.

8. During construction of the installation, ensure that no dirt, water, or

residue from welding is left in the system.

9. Consider expansion joints or pipe loops to accommodate thermal

expansion. Design should be per latest edition of ASHRAE Systems and
Equipment Handbook to prevent detrimental forces and stresses at
connected equipment. Thermal expansion should be calculated using the
maximum possible utilization fl uid temperature, regardless of whether the
pipe considered is in the feed or return circuit. Steel pipe will grow axially
and can be expected to expand approximately 1” over 100ft @ 100dg F
temperature rise (1mm per meter over 100 C rise).

10. Provide properly designed supports and anchors for all piping where

necessary to prevent undue stress from being imparted on equipment
such as pumps, valves and the heater. Care should be taken as end
reactions transmitted to rotating equipment, such as pumps, may deform
the equipment. Therefore equipment manufacturers’ recommendations
on allowable forces and movements should be followed. See Figure 8.

11. Ensure all pipe joints are of either welded or fl anged construction. Screwed

joints must be avoided where possible. In no instance should screwed
joints be used in the fl ow circuit. All fl anges should be welded to the pipe
and not screwed. Depending on the size, fl anges should be 150# or 300#
raised face fl anges, SA105.

12. Ensure heaters that are skid mounted with pumps and tanks are equipped

with a y-strainer, a fl ex connector and a valve in the inlet run between the
pump and the combination tank. Piping between the discharge of the
pump and the inlet of the heater will include a fl ex connector and a valve.

13. If screwed connections have to be made, e.g., to items of control

equipment, use a thread sealant suitable for use with fl uids at elevated
temperature. Tefl on tape, standard pipe sealant, or hemp and paste are not
acceptable.

14. Cut screw threads carefully and accurately. If possible, new tools should

be used. Threaded connections larger than 1” are not to be used. It is
recommended that GR5 or higher tensile steel bolts be used for all fl anged
joints.

15. Use gaskets to make all fl anged connections. Gasketing material must be

suitable for use with the pressure, temperatures and fl uids in the system.
Flexible graphite gaskets are suited for most applications. Recommended
gasket thickness is 1/10 - 1/8 inch. Ensure that all bolts are tightened
evenly and to the torque recommended values provided by the gasket
manufacturer. Refer to Figure 9 and Tables 5-8 for guidelines.

NOTE: Typical gaskets used by Fulton include JM Clipper Elastograph gaskets and

Flexitallic gaskets. Adhere to installation instructions and torque requirements for
these gaskets.

16. Install high point bleeds at all high points in the system piping. 1/2” x 12”