Fulton Vertical Tubeless (FT-A) Thermal Fluid (hot oil) Heater User Manual

Page 3

Advertising
background image

Questions? Call (315) 298-5121, or visit us online at www.fulton.com

FTA-IOM-2013-0227

TABLE OF CONTENTS

0-1

Introduction

1-1

Overview .............................................................................................................. 1-2
Warnings & Cautions ............................................................................................ 1-2
Disclaimers and Local Codes ................................................................................ 1-2

Installation

2-1

Placement & Rigging ........................................................................................... 2-2
Clearances & Serviceability .................................................................................. 2-3
Environment, Ventilation and Combustion Air Requirements ............................ 2-3
Utilities ................................................................................................................. 2-7

THE GAS SUPPLY ..........................................................................................................................2-7

THE OIL SUPPLY ...........................................................................................................................2-7

Instrument Air ...................................................................................................... 2-8
Electrical Supply ................................................................................................... 2-8
Thermal Fluids .................................................................................................... 2-10

THERMAL FLUIDS AT ELEVATED TEMPERATURES ....................................................................2-10

SELECTING A THERMAL FLUID ..................................................................................................2-11

ROUTINE ANALYSIS OF HEAT TRANSFER FLUID ........................................................................2-12

THERMAL FLUID BREAKDOWN .................................................................................................2-12

Piping Specifi cations .......................................................................................... 2-14
Insulation ........................................................................................................... 2-20
System Interfaces ............................................................................................... 2-20

HEATER CONNECTIONS ..............................................................................................................2-20

THERMAL FLUID CIRCULATING PUMP .....................................................................................2-20

REQUIREMENTS FOR AIR COOLED PUMPS ..............................................................................2-22

REQUIREMENTS FOR WATER COOLED PUMPS .........................................................................2-22

COMBINATION DEAERATOR/THERMAL BUFFER/EXPANSION TANK ........................................2-22

SIZING THE EXPANSION TANK FOR THE SYSTEM ......................................................................2-23

PRESSURIZED SYSTEMS ............................................................................................................2-23

VENT CONNECTIONS ..................................................................................................................2-26

CATCH TANK ...............................................................................................................................2-27

DRAIN/FILL CONNECTION .........................................................................................................2-27

PRESSURE GAUGES ...................................................................................................................2-27

THERMOMETERS .......................................................................................................................2-27

VALVES .......................................................................................................................................2-28

AUTOMATIC FLUID CONTROL VALVES .......................................................................................2-29

BY-PASS VALVES ........................................................................................................................2-29

Assembly of Fulton Multi-Skid Engineered Systems ......................................... 2-30
Stack and Flue .................................................................................................... 2-31
Testing ................................................................................................................ 2-32

Operation

3-1

Start-Up Preparation & Installation Review ........................................................ 3-2
Fill the System ...................................................................................................... 3-2

FILLING PROCEDURE FOR SYSTEMS OPEN TO ATMOSPHERE ....................................................3-3

FILLING PROCEDURE FOR SYSTEMS EQUIPPED WITH INERT BLANKETS .................................3-3

Circulating Pump .................................................................................................. 3-4

PUMP WITH MECHANICAL/AIR COOLED SEAL ...........................................................................3-5

PUMP WITH PACKED SEAL ..........................................................................................................3-6

Start-Up Service ................................................................................................... 3-6
Initial Start-Up ..................................................................................................... 3-6

COLD CIRCULATION......................................................................................................................3-6

FILTERING THE SYSTEM ...............................................................................................................3-7

BOILOUT .......................................................................................................................................3-8

COMBUSTION ...............................................................................................................................3-9

Flame Programmers .......................................................................................... 3-12
Operating Controls ............................................................................................. 3-12

LIQUID LEVEL SWITCH - WHEN COMBINATION TANK IS SUPPLIED ........................................3-12

AIR SAFETY SWITCH ..................................................................................................................3-12

BLOWER MOTOR STARTER .........................................................................................................3-13

PUMP MOTOR STARTER .............................................................................................................3-13

DIFFERENTIAL PRESSURE SWITCH ...........................................................................................3-13

HIGH AND LOW FLUID PRESSURE SWITCHES ...........................................................................3-14

GAS PRESSURE SWITCH ............................................................................................................3-15

OPERATING TEMPERATURE CONTROLS ....................................................................................3-15

HIGH TEMPERATURE LIMIT SWITCHES SAFETY ......................................................................3-16

OPERATING LIMIT CONTROLLER ...............................................................................................3-17

ON/OFF CONTROLS ....................................................................................................................3-17

MODULATING CONTROLS ..........................................................................................................3-17

PRESSURE GAUGES ....................................................................................................................3-17

TEST OF IGNITION SAFETY SYSTEM SHUTOFF ..........................................................................3-18

CYCLE TESTING ...........................................................................................................................3-18

Required Pressure Drop Across the Heater ......................................................... 3-18
Procedure for First Shutdown ............................................................................ 3-19
Daily Start-Up ..................................................................................................... 3-19
Daily Shutdown .................................................................................................. 3-20
Before Leaving the Installation .......................................................................... 3-20

Maintenance

4-1

Required Equipment ............................................................................................ 4-2
Required Maintenance at First Shutdown ........................................................... 4-2
Daily Maintenance Schedule ................................................................................ 4-2
Weekly Maintenance Schedule ............................................................................ 4-3
Monthly Maintenance Schedule .......................................................................... 4-3
Semi-Annual Maintenance Schedule .................................................................. 4-4
Annual Maintenance Schedule ........................................................................... 4-4
General Maintenance Procedures ....................................................................... 4-5

LUBRICATION ...............................................................................................................................4-5

SOOT CLEANING ..........................................................................................................................4-5

Safety Check Procedures ..................................................................................... 4-5

LIQUID LEVEL SWITCH ................................................................................................................4-5

Advertising