Installation consists of the following:

Foundation check, layout, and base plate setting

Tools, materials, documentation, and a crane

Setting the modules

Setting the modules on load cells

A. Preparations for Installation: Tools, Equipment, and Materials Required

1.

Certified Prints

2.

A mobile crane of sufficient capacity to safely lift and place the weighbridge

modules.

Approximate Steel Deck Module maximum weight: 8 tons.

3.

Four (4) equal length (20 ft) lifting chains or cables with hooks to safely attach to the

modules lifting channels located on the sides of the modules.

4.

Machinist’s levels (Starrett # 134 & 132-6)

5.

Hand tools

6.

Hammer Drill with

5

/

8

" bit, 16" long

7.

Hydraulic jacks, 16 ton capacity

8.

100' steel tape measure

9.

Stringline and chalkline

10. Prybars

11. High-quality grease and anti-seize

12. Load cell locating tools, Part No. 707118

50745

7

03/10 Rev. 5

Section 3: Installation

Note: The lifting straps MUST be requested in advance from the Crane Service Company.