Fairbanks HVX Series TALON SERIES Motor Truck Scale User Manual
Page 26
F. Grounding,
SSCs
1.
Intalogix™ systems must have two (2) ground rods in the pit for proper connection.
Pit power supplies use a ground separate from the steel and SSC ground rod.
G. Indicator-to-Pit Power Supply Cable Connection
Prepare the cable ends in the standard manner. Use the appropriate manual for wiring
instructions of all pit SSCs and power supplies. Connect the indicator interface cable to
the instrument in the scale house per the instructions in the appropriate indicator service
manual.
50785
26
04/12 Rev. 5
Note: SSCs have connections for 2 load cells, TB 1 and TB 2. The odd numbered cell
should go to TB1 connection, and the even numbered cell to TB2 connection.
Note: Intalogix
TM
installations utilize a different numbering system for load cells because of
digital addressing of the SSCs. Number the load cells as follows: With respect to
the following starting position, face the platform from where the indicator is located.
The cell at the upper left (far side) of the platform is Cell 1. The cell positions along
the far side will be odd cell number; the near side locations will be even cell
numbers.