4.3 Power-On Procedure

4.3.1 Installation Checklist

WARNING:

Make sure a power supply with the correct input voltage is being fed into

the system. Incorrect voltages applied to the system may cause damage to

the internal electronic components and may also cause injury to the user.

To power on the embedded system please make sure of the following:

The memory module is installed

The wireless LAN module is installed

The CF module is installed

The bottom cover is installed

All peripheral devices (VGA monitor, serial communications devices etc.) are

connected

The power cables are plugged in

The system is securely mounted

4.3.2 Power-on Procedure

To power-on the IBX-530B-N270 please follow the steps below:

Step 1:

Turn on the power switch.

Step 2:

Once turned on, the green power LED should be turned on. See Figure 4-12.