6.1 Preparation for Starting

Operation

This section describes the operation procedure

for the EJ118 as shown in Figure 6.1 when

measuring liquid level in a closed tank, and

EJ438 as shown in Figure 6.2 when measuring

pressure in a tank.
(a) Confirm that there is no leak in the connecting

part of each diaphragm seal mounting flange.

(b) Turn ON power and connect the communicator.

Open the terminal box cover and connect

the communicator to the SUPPLY + and

– terminals.

(c) Using the communicator, confirm that the

transmitter is operating properly. Check

parameter values or change the setpoints as

necessary.

See IM 01C25T03-01E (BRAIN

communication) or IM 01C25T01-06EN (HART

communication) for communicator operation.

If the transmitter is equipped with an integral

indicator, its indication can be used to confirm

that the transmitter is operating properly.

F0601.ai

Closed tank

Transmitter mounting pipe

50mm (2 inches)

Capillary tube

Differential pressure

transmitter

Diaphragm seal

(high pressure side)

Diaphragm seal

(low pressure side)

Figure 6.1

Liquid Level Measurement in a Closed

Tank

F0602.ai

Transmitter mounting pipe

50mm (2 inches)

Capillary tube

pressure transmitter

Diaphragm seal

(high pressure side)

Figure 6.2

Pressure Measurement

■ Confirming that Transmitter is Operating

Properly

Using the BT200

• If the wiring system is faulty, ‘communication

error’ appears on the display.

• If the transmitter is faulty, ‘SELF CHECK

ERROR’ appears on the display.

communication error

PARAM

C60:SELF CHECK

ERROR

Communication error

(Faulty wiring)

Self-diagnostic error

(Faulty transmitter)

DATA

DIAG

PRNT

ESC

F0603.ai

Advertising