Startup

The following should be used as a guide for a compre-

hensive commissioning and startup procedure which is

required before placing your Mammoth unit into service.

IMPORTANT! The commissioning and startup

procedures described in this document must

be carried out prior to placing this unit into

service. Failure to follow these procedures

could result in improper or dangerous opera-

tion and/or void the equipment warranty.

CAUTION! Installation, startup and servicing

of this equipment should only be undertaken

by trained professionals with experience

working on commercial HVAC systems. Con-

tact your Mammoth representative or the

Mammoth Service Department for help in

scheduling service.

Startup Report Form

A startup report form is zip-tied to the inside of the main

control panel. In addition to carrying out the procedures

described in this guide, it should be filled out, signed and

returned to Mammoth as part of the warranty process for

your system. See the warranty documents included with

your unit for additional information.

Prior to Startup

Before requesting unit startup, please verify all of the fol-

lowing.

The main power supply is connected to the unit dis-

connect and electrical power is available to run the

unit.

Drain lines are connected to the condensate connec-

tions. See “Condensate drain” on page 17.

The controls contractor has been notified of the

requested start-up date and is confirmed to attend.

The duct system is complete enough to allow for

operation.

All air filters have been installed.

All water systems, if applicable, have been fully

installed, tested and will be operable.

Startup: Power Off

Verify that the system on/off and/or standby switch is in

the off or standby position. Then carry out the following

procedures.

WARNING! Electric shock and moving equip-

ment hazard. Can cause severe injury or

death. Lock and tag out all electric power

before carrying out these procedures. More

than one disconnect may be required to de-

energize the unit..

Electrical

Electrical Terminals
Tighten all electrical terminals per the torque value listed

on the connector. Electrical terminals are located within

the main unit control panel. Where no torque value is

given, use the tightening torques provided in this manual.

See “Electrical Terminal Tightening Torques” on page

19.

WARNING! Loose electrical terminals can

lead to erratic unit operation and arcing which

may cause fires. Tighten all electrical ter-

minals before unit startup. Be careful not to

over-tighten to avoid stripping out threads..

Motor Protector Settings
Before startup, adjust the overload setting on all motor

protectors as follows. They are located within the unit

electrical panel. See Figure 14.
Figure 14: Motor Protectors

Adjust motor protector amp settings to match electrical

schematics or motor nameplates

1. Switch to the off position all motor protectors.
2. For motors and pumps, adjust the setting to match

the amps (FLA) listed on the motor nameplate.

3. For compressors and VFDs, adjust the setting as

indicated on the electrical wiring diagram provided

with your unit.