INSTALLATION

3

19

OPTISONIC 3400

www.krohne.com

11/2013 - 4002037702 - HB OPTISONIC 3400 -en-R02

3.4 Pre-installation requirements

Make sure that you have all necessary tools available:

• Allen key (4 mm)
• Small screwdriver
• Wrench for cable glands
• Wrench for pipe mounting bracket (remote version only) see; on page 25
• Torque wrench for installing flowmeter in pipeline

3.5 General requirements

3.5.1 Vibration

INFORMATION!
To assure a quick, safe and uncomplicated installation, we kindly request you to make provisions
as stated below.

INFORMATION!
The following precautions must be taken to ensure reliable installation.

•

Make sure that there is adequate space to the sides.

•

Protect the signal converter from direct sunlight and install a sun shade if necessary.

•

Signal converters installed in control cabinets require adequate cooling, e.g. by fan or heat
exchanger.

•

Do not expose the signal converter to intense vibration. The flowmeters are tested for a
vibration level in accordance with IEC 68-2-6.

Figure 3-2: Avoid vibrations

INFORMATION!
In case of expected vibrations, please install a field version.