Installation – Alliance Laundry Systems HC35 User Manual

Page 41

Advertising
background image

39

Installation

F232062

Figure 32

Note: Check and retighten the locknuts after
five to ten days of operation and every three
months thereafter.

Figure 33 shows the completed J-bolt
installation with grout.

Figure 33

Concrete Foundation Pad

A concrete foundation pad may be constructed
to elevate the machines. See Figure 34 for a
typical concrete foundation pad installation.

Note: Expansion bolts should not be used
in single-machine concrete foundation
pad installations.

1. Verify that the floor is 3500 psi minimum

reinforced concrete embedded in clean,
compacted fill dirt. For 2-speed models,
the floor must be at least 4 inches
(102 mm) thick. For 3-speed and variable-
speed models (except for the 80-pound
capacity model), the floor must be at least
6 inches (152 mm) thick. For 80-pound
capacity models, the floor must be at least
9 inches (229 mm) thick.

2. Break up and excavate the floor to a depth

of approximately 9 inches (230 mm)
below the floor surface, making certain
that the sides of the hole slope outwards
from top to bottom.The bottom of the hole
should be 5 inches (127 mm) larger all
around than the top.

Note that when installation is complete,
the top of the pad should extend a
minimum of 4 inches (102 mm) out from
the machine on all sides.

3. Wet the hole well and brush the bottom

and sides with cement grout.

H033I

H034IE1A

Locknut

Machine

Base

J-Bolt

1/2 in. (13 mm)

Machinery

Grout