background image

Check

Explanation/comment

Checked

For outside tank mount and dry pit

applications, install an isolation valve in the

suction line at least two pipe diameters

from the suction.

This allows the line to be closed for pump

inspection and maintenance. The isolation valve

must be kept fully open during operation.

Make sure that the entrance to the suction

pipe is kept adequately submerged below

the free liquid surface.

This prevents vortices and air entrainment.

For an outside tank mount application,

make sure that a column assembly is

installed.

The column assembly allows the fluid that comes

through the lower bushings to flow up through the

column and back through the connection at the

top of the column back to the tank.
Connect the pipe at the top of the pump column

back to the source tank in order to prevent fluid

from entering the thrust bearing.

Steam lines

Precautions

WARNING: Use proper safety precautions when dealing with high pressure air or fluid.

Checklist

Check

Explanation/comment

Checked

Before you install the pump,

become familiar with the location

of the steam lines.

There are three connections above the support plate:

• Two steam connections
• One condensate return connection.

The steam connections are connected to the tops of the

column and discharge jackets.

Determine which method to use

in order to connect the steam lines.

There are two methods you can use in order to connect

the steam lines:

• You can use both steam lines as input for steam

(preferred method).

• You can use one steam line as input for steam, while

the other steam line is used as a feed through to
additional pumps.
Only use this method if absolutely necessary,

because it is difficult to control the steam at

subsequent pumps.

Before you install the pump,

check the fittings for leaks. Use

plant air or high pressure water.

The jackets are hydrotested by the factory at 100 psi

before shipment. However, the tube fittings can become

loose during transit.
If you use air to check for leaks, use a soap solution at

each joint in order to check for air bubbles.

Provide source of steam at 35 psi

and 300°F (149°C).

Less than ideal conditions require higher pressure steam

in order to keep the correct temperature.

After the pump is brought to

temperature for the first time,

shut down the unit temporarily

and readjust the impeller clearance.

Refer to Impeller clearance setting in the Operations

chapter.

Installation (Continued)

Model 3171 Installation, Operation, and Maintenance Manual

21