Burnham CHG225 User Manual
Page 18
 
1
Figure 6.: Z-Vent iii Connection to Vent Collar
i)				Align	the	second	piece	of	pipe	with	the	first	and	push	them	together	as	far	as	they	will	go,	but	not	less	
	 	than	1-3/4”.
j)		 	Tighten	gear	clamp	to	a	minimum	torque	of	40	in-lbs	and	a	maximum	of	50	in-lbs.
k)	 	Repeat	Steps	(h)	–	(j)	for	the	remaining	Z-Vent	III	components.	
l)	 In	horizontal	vent	systems,	a	locking	band	or	gear	clamp	must	be	used	at	either	side	of	the	wall	penetration		 	
to prevent shifting of the vent system in and out of the wall. This applies to both combustible and non-
combustible walls.
n) Allow the silicone to cure per the silicone manufacturer’s instructions before operating the boiler.
6) Assembly of Heat Fab Saf-T Vent EZ Seal:
a)	 	Saf-T	Vent	General	Notes:
	 	These	instructions	cover	the	installation	of	Saf-T	Vent	EZ	Seal.	Saf-T	Vent	EZ	Seal	piping	has	integral		
gaskets	installed	in	the	female	ends	of	the	pipe	which	seal	the	joints.			
•	 In	general,	Saf-T	Vent	pipe	sections	may	not	be	cut.	Exceptions	to	this	are	the	Saf-T	Vent	slip		 	
connector and connections to the boiler vent collar. In these cases, use a sharp pair of aviation snips, an
abrasive cut-off, or a plasma cutter. See the Saf-T Vent instructions for information on cutting the
slip connector.
•	 Orient	Saf-T	Vent	components	so	that	the	arrows	on	the	piping	labels	are	in	the	direction	of	flue	gas	flow.
•	 Support	horizontal	piping	sections	at	intervals	of	6	feet	or	less.
•	 Vertical	venting	systems	must	be	supported	by	at	least	one	Heat	Fab	support.	An	additional	vertical		
support is required after any offset.
b) Connection to Boiler – Start assembly of the vent system at the boiler. Remove the hose clamp shipped on the
CHG vent collar. Bend the three hose clamp tabs on this collar outward slightly. Cut the male
spigot” off of the first piece of pipe (Fig 6.9). If necessary, crimp the cut end of the pipe so that it can
be inserted at least 1” into the collar. Clean the exterior of the male end of the first piece of pipe and the
inside of the vent collar on the boiler with an alcohol pad. On the male end of the pipe, apply a ¼” wide
bead of high temperature silicone approximately ½ inch from the male end of the pipe. Also apply a ¼”
bead of silicone along the first 2 ½” of the longitudinal weld. Insert the male end of the pipe into the boiler
vent collar until it bottoms out. Apply an additional bead of silicone over the outside of the joint and
smooth out (Fig 6.9). Replace and tighten the clamp on the vent collar.
c) Assembly of Saf-T Vent EZ Seal Vent Components - Clean the male end of the next piece of pipe with an
alcohol pad and make sure that it is free of burrs. Check the female end of the first piece of pipe to make
sure that the gasket is in place and is undamaged. Using a slight twisting motion, insert the male end of the
second fitting into the female end of the first fitting, taking care not to dislodge or cut the factory gasket.
In extremely arid conditions, it may be easier to assemble these fittings if the gasket is moistened with
water prior to assembly. Bend the locking tabs over the locking ring on the adjacent piece of pipe. Repeat
these steps for the remaining Saf-T-Vent components.