7) Start the boiler using the lighting instructions on page 40. After the boiler is powered up, it should go through

the following sequence.

Sequence Display

Meaning

1

U.125

or Blank

Checking internal software (power-up only)

2

0.SWT

Boiler in standby.

SWT

= Supply Water Temp. No call for heat.

(After call for heat from heating thermostat)

3

A.SWT

Self-Check on Start-up

4

5.SWT

Blower and circulator on. Checking for adequate air flow.

5

1.SWT

Prepurge

6

2.SWT

Trial for ignition

7

3.SWT

Flame established. Boiler responding to a call for heat.

8) Upon initial start-up, the gas train will be filled with air. Even if the gas line has been completely purged of air,

it may take several tries for ignition before a flame is established. If more than 5 tries for ignition are needed,

it will be necessary to press the reset button to restart the boiler. Once a flame has been established for the first

time, subsequent calls for burner operation should result in a flame on the first try.

9) Inspect the flame visible through the window. On high fire the flame should be stable and mostly blue

(Fig.10.1). No yellow tipping should be present; however, intermittent flecks of yellow and orange in the flame

are normal.

10) Check the inlet pressure and adjust if necessary. Verify that the inlet pressure is between the upper and lower

limits shown on the rating plate with all gas appliances on and off.

Figure 10.1: CHG Burner Flame

warNINg

ThE COrrECT OuTlET PrEssurE fOr ThE gas ValVE has bEEN

faCTOry sET aND rEquIrEs NO fIElD aDJusTmENT. ThIs sETTINg Is

saTIsfaCTOry fOr bOTh NaTural gas aND PrOPaNE. aTTEmPTINg TO

aDJusT ThE OuTlET PrEssurE may rEsulT IN DamagE TO ThE gas

VALVE AND CAuSE PRoPERTy DAMAGE, PERSoNAL INjuRy oR LoSS oF

lIfE.

Advertising
This manual is related to the following products: