17. Install the 3/8-16 UNC x 1” bolts as shown with washers under the head of the bolts,
and flange nuts on the underside. Snug hardware down to secure A-pillar floor plate.
18. Next, install the frame tie in as shown and prep area for welding. However, do not
weld at this time.
19. With the A-pillar floor plates and cage tie-ins mocked into position, we will begin
fitting the A-pillars behind the dash.
20. We will start by removing a few key components of the dash to allow for easier
trimming to fit the A-pillars.