SECTION 4 - HYDRAULICS

4-28

– JLG Lift –

3121249

8. Remove the charge pump outer ring (S150), and

gearset (S100).

9. Remove valve plate (S250) with seal (S300). Discard

seal

INSPECTION:

10. Inspect the components for wear, scratches or pit-

ting. Carefully inspect the valve and pressure-bal-
ance plates. Scratches on these components will
cause a loss of charge pressure. If any component
shows signs of wear, scratching or pitting, replace it.

REASSEMBY:

11. Install new seals (S300) in the valve (S250) and

pressure-balance (S200) plates.

12. Install valve plate (S250) in the same orientation as

removed.

13. Lubricate and install charge pump (S100) and outer

ring (S150).

14. Install charge pump coupling (K200).

15. Install pressure balance plate (S200) in the same ori-

entation as removed.

16. Install the thrust washer (K500). Coated side goes

toward charge pump coupling (K200).

17. Install a new cover gasket. (K150). If removed, install

guide pins (K450).

18. Install the auxiliary pad or charge pump cover and

cap screws. Using a 10mm internal hex wrench,
torque the cap screws (K400) to 68 lb-ft (92 Nm).
Torque in sequence below.

19. Reinstall auxiliary pump or pad seal (K250) and

shipping cover (K300).

.

SAE B

SAE A

K400

8 mm

K300

K350

(see table)

K250

Auxilliary pads

1

2

3

4

Torque sequence

Cover Screw K350

Cover Pad

Wrench Size; Torque

A

17 mm; 35 lb-ft (48 Nm)

B, C

19 mm; 58 lb-ft (77 Nm)

K500

S100

S300

S200

K200

K150

K400
8 mm

K100

S300

S250

G450

G450

Charge pump removal/installation