SECTION 4 - MACHINE OPERATION

4-24

– JLG Lift –

3128792

To lift the machine a separate sling must be attached to each
outrigger using the appropriate lifting points as indicated in the
photo.

As the weight of the machine is not spread equally over the
four outriggers, the minimum required capacity of the four
ropes, chains or slings used must be: no less than 4,409 lb.
(2000 kg) and their length no less than 10 ft. (3m) and all iden-
tical.

Tie Down

(See Figure 4-6.)

WHEN TRANSPORTING THE MACHINE, THE BOOM MUST BE FULLY
LOWERED INTO THE BOOM REST.

• Travel up ramps with the platform behind the machine.
• Do not contact the ground with the jib or bottom of plat-

form when loading/unloading.

• ALWAYS load/unload the machine with the track fully

widened.

1. Place the booms in the stowed position.

2. Remove all loose items from the machine.

3. Secure the machine using straps or chains of ade-

quate strength.

DO NOT MAKE CONNECTIONS AT POINTS DIFFERENT THAN
THOSE IDENTIFIED BY THE TIE DOWN LOCATION DECAL SHOWN.
THIS COULD CAUSE PERMANENT DAMAGE RESULTING IN THE
COLLAPSE OF THE PRODUCT.

Figure 4-5. Lifting Machine - Attach Points

1. Lifting Slings