4.4 MACHINE SET-UP AND OPERATION

The following sequence of set-up procedures must be followed
to safely operate this machine.

1. Position machine in work area. Work area must be a

smooth, firm, level surface.

NOTE: Check that battery box assembly is installed, battery is

charged and connected to the machine’s DC receptacle.

2. Set Power On/Off Key Switch to the ON position at the

ground control station.

3. Check both Emergency Stop switches, one on platform

control station and one on ground control station, they
must be in the reset position for operation.

4. Set Floor Stop, see steps following.

Floor Stop Operation

(See Figure 4-4. on page 4-6)

1. Located on both sides of the machine under the base

frame, behind either of the front caster wheels, are the
floor stop assemblies. Engage and lock one or both of the
floor stop assemblies down into position

THE FRONT CASTER WHEELS SHOULD BE RELI EVED OF THE
MACHINES WEIGHT ENOUGH SO THE MACHINE DOES NOT ROLL IN
ANY DIRECTION. IF THIS IS NOT THE CASE DO NOT ATTEMPT TO ELE-
VATE THE PLATFORM UNTIL THE FLOOR STOP IS OPERATING PROP-
ERLY.

2. To disengage the floor stop, apply pressure to the release

rod or lift up on the floor stop pedal.