2 the commissioning steps in detail, 1 planning the bus topology, 2 installing field devices – Lenze PROFINET Controller-based Automation User Manual

Page 21: The commissioning steps in detail, Planning the bus topology, Installing field devices, Planning the bus topology ( 21), 6commissioning of the profinet

Advertising
background image

Lenze · Controller-based Automation · PROFINET® Communication Manual · DMS 1.2 EN · 04/2014 · TD17

21

6

Commissioning of the PROFINET

6.2

The commissioning steps in detail

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

6.2

The commissioning steps in detail

In the following sections, the individual commissioning steps are described.
Follow the instructions of these sections step by step in order to commission your system.

6.2.1

Planning the bus topology

Before installing a PROFINET network, make a diagram of the network.

How to plan the bus topology for your configuration

1. Create an overview of the planned PROFINET network with all field devices to be

integrated.

2. Start with the I/O master.
3. Add the other field devices (I/O devices) below.

6.2.2

Installing field devices

For the installation of a field device, follow the mounting instructions for the respective device.

More detailed information about how to work with the Lenze Engineering tools can be

found in the corresponding manuals and online helps.

Mounting instructions of the field devices
Observe the safety instructions.

Advertising