This chapter describes procedures to mount the M2A Transmitter in the monitoring environment
and wire it to input power and devices.

Mounting the M2A Transmitter

1.

Select a mounting site that is representative of the monitoring environment. Consider the
following when you select the mounting site.

Select a site where the M2A is not likely to be bumped or disturbed. Make sure there is
sufficient room to perform start-up, maintenance, and calibration procedures.

Select a site where the target gas is likely to be found first. For lighter gases, mount the
detector near the ceiling; for heavier gases, mount the detector near the floor.

2.

At the monitoring site, use #10 screws through the junction box’s two mounting holes to secure
the junction box to a vertical surface. Figure 11 - Figure 16 show the outline and mounting
dimensions for each version of the M2A. Mount the M2A with the detector facing down as
shown in the following figures.

Figure 11: Outline & Mounting Dimensions, Catalytic LEL

2.3 max

7.7 max

1.02

5.86

4.59

3/4 NPT
Conduit Hub

.47 (2X)

.30 (2X)

2.41

5.00

5.23

1 1/2-20 For
Calibration Cup