14

Safety Function: Hinge Switch

Rockwell Automation Publication SAFETY-AT096A-EN-P – November 2013

GSR Emergency Stop Safety Function Verification and Validation Checklist (continued)

General Machinery Information

Machine Name/Model Number

Machine Serial Number

Customer Name

Test Date

Tester Name(s)

Schematic Drawing Number

Guardmaster Safety Relay Model

Safety Wiring and Relay Configuration Verification

Test Step

Verification

Pass/Fail Changes/Modification

Visually inspect the safety relay circuit to verify that it is

wired as documented in the schematics.

Visually inspect the safety-relay rotary switch settings to

verify they are correct as documented.

Normal Operation Verification

The safety relay system properly responds to all normal Start, Stop, E-stop, and Reset

commands.

Test Step

Verification

Pass/Fail Changes/Modification

Initiate a Start command. Both contactors energize for a

normal machine run condition. Verify proper machine-status

indication and safety-relay status indication.

Initiate a Stop command. Both contactors de-energize for a

normal machine Stop condition. Verify proper

machine-status and safety-relay status indication.

While the system is running, press the E-stop button. Both

contactors de-energize and open for a normal safe

condition. Verify proper machine-status indication and

safety-relay status indication. Repeat for all E-stop buttons.

While the system is stopped, press the E-stop button and

initiate a Start command. Both contactors remain

de-energized and open for a normal safe condition. Verify

proper machine-status indication and safety-relay status

indication. Repeat for all E-stop buttons.

Initiate a Reset command. Both contactors remain

de-energized. Verify proper machine-status indication and

safety-relay status indication.