5. Check height of feeder in relationship to

register by placing a 1mm thick (approx.) object that
will sit on top of register ribs without being held. A
common 12 inch scale placed at an angle on top of the
register ribs is a good example of what to use. The top
surface of the 1mm thick object should be in line with
the top surface of rake plate fingers on the pile feeder.
Adjust casters on pile feeder accordingly to achieve
this height relationship between the pile feeder and
register.

6. Level the feeder by adjusting casters on pile

feeder accordingly. Once pile feeder has been leveled,
lock the height adjustment in place by locking the nuts
on the casters down on the feeder tie bars.

7. Hook up air blow and vacuum hoses on

feeder to corresponding holes on 1st station folding
unit manifold.

8. Connect double sheet detector cable on

pile feeder to double sheet detector on register.

9. Connect communication cable on pile

feeder to connector on 1st station folding unit. The
connector on 1st station folding unit is the same (9) pin
connector used for connecting the short pile feeder
table.

10. The pile feeder is designed to provide

electrical power to both the 1st and 2nd station folding
units. The receptacles for the 1st and 2nd station
folding units are located on the operator side guard.
Plug the 1st and 2nd station folding units into the
receptacles provided on the pile feeder.

11. Plug the pile feeder into the proper type

and size of wall receptacle. Refer to page #9 of this
manual for electrical requirements.