2 mechanical planning, Mechanical planning, Figure 1. gate position – Unitec American Parking Equipment User Manual

Page 6

Advertising
background image

Document

Number:

GC1001

2

Document Title:

Unitec APE Gate and Gate Controller for Multi-Lane Applications Installation Guide

You will need the following 1” conduit runs in place:

• A conduit between the gate controller (located in the equipment room) and

the WSII/Portal units to carry communication wiring.

• A conduit between the breaker and the WSII/Portal units to carry 115-

120VAC wiring.

• A conduit between the gates and the WSII/Portal units to carry gate signal

wiring.

• A conduit between the gates and the WSII/Portal units to carry 115-120VAC

wiring.

• If there is a merge zone loop installed, a conduit to carry the merge zone loop

leads to the gate. Each merge loop must be connected to its respective gate.

1.2 Mechanical Planning

Position the gate so that the gate arm is 10’-12’ from the WSII/Portal centerline in line with
the WSII/Portal unit.

Figure 1. Gate Position

The following figure illustrates a sample site layout.

Advertising