OUT

TEE

NIPPLE

CAP

IN

C99020

Fig. 7 -- Sediment Trap

5. Install an accessible, external, manual main shutoff valve in

gas supply pipe within 6 ft (1.8 m) of heating section.

6. Install ground--joint union close to heating section between

unit manual shutoff and external manual main shut--off

valve.

7. Pressure test all gas piping in accordance with local and

national plumbing and gas codes before connecting piping
to unit.

NOTE: Pressure test the gas supply system after the gas supply
piping is connected to the gas valve. The supply piping must be
disconnected from the gas valve during the testing of the piping
systems when test pressure is in excess of 0.5 psig. Pressure test the
gas supply piping system at pressures equal to or less than 0.5 psig.
The unit heating section must be isolated from the gas piping
system by closing the external main manual shutoff valve and
slightly opening the ground--joint union.

FIRE OR EXPLOSION HAZARD
Failure to follow this warning could result in personal injury,

death and/or property damage.
--Connect gas pipe to unit using a backup wrench to avoid

damaging gas controls.

--Never purge a gas line into a combustion chamber. Never

test for gas leaks with an open flame. Use a commercially

available soap solution made specifically for the detection of

leaks to check all connections.

--Use proper length of pipe to avoid stress on gas control

manifold.

--If a flexible connector is required or allowed by authority

having jurisdiction, black iron pipe shall be installed at

furnace gas valve and extend a minimum of 2 in. (51 mm)

outside furnace casing.

--If codes allow a flexible connector, always use a new

connector. do not use a connector which has previously

serviced another gas appliance.

!

WARNING

8. Check for gas leaks at the field--installed and

factory--installed gas lines after all piping connections have

been completed. Use a commercially available soap solution

made specifically for the detection of leaks (or method
specified by local codes and/or regulations).

Step 9 — Install Duct Connections

The unit has duct flanges on the supply-- and return--air openings
on the side and bottom of the unit. For downshot applications, the

ductwork connects to the roof curb (See Fig. 2 and 3 for
connection sizes and locations).

Configuring Units for Downflow (Vertical) Discharge

ELECTRICAL SHOCK HAZARD
Failure to follow this warning could result in personal injury

or death.
Before installing or servicing system, always turn off main

power to system. There may be more than one disconnect

switch. Tag the disconnect switch with a suitable warning

label.

!

WARNING

1. Open all electrical disconnects before starting any service

work.

2. Remove horizontal (metal) duct covers to access vertical

(downflow) discharge duct knockouts in unit basepan. (See
Fig. 8.)

3. Starting in a corner as shown in Fig. 9, score the panel in

both directions from the corner. Tap the panel out from the
scored corner using a small hammer. Be careful and not

damage any other part of the unit.

4. If unit ductwork is to be attached to vertical opening flanges

on the unit base (jackstand applications only), do so at this

time.

PROPERTY DAMAGE HAZARD
Failure to follow this caution may result in property damage.
Collect ALL screws that were removed. Do not leave screws

on rooftop as permanent damage to the roof may occur.

CAUTION

!

5. It is recommended that the base insulation around the

perimeter of the vertical return--air opening be secured to
the base with aluminum tape. Applicable local codes may

require aluminum tape to prevent exposed fiberglass.

6. Reinstall both horizontal duct covers. Ensure opening is

air-- and watertight.

7. After completing unit conversion, perform all safety checks

and power up unit.

NOTE: The design and installation of the duct system must be in

accordance with the standards of the NFPA for installation of

nonresidence--type air conditioning and ventilating systems, NFPA

90A or residence--type, NFPA 90B; and/or local codes and

ordinances.
Adhere to the following criteria when selecting, sizing, and

installing the duct system:

1. Units are shipped for horizontal duct installation (by

removing duct covers).

2. Select and size ductwork, supply--air registers, and

return--air grilles according to American Society of Heating,
Refrigeration and Air Conditioning Engineers (ASHRAE)

recommendations.

3. Use flexible transition between rigid ductwork and unit to

prevent transmission of vibration. The transition may be
screwed or bolted to duct flanges. Use suitable gaskets to
ensure weather tight and airtight seal.