Crating The Pedestal

1.

Place the base of the crate close to the pedestal, leaving room for the ramp.

2.

Using two or more people, insert the two pins at the end of the ramp into
the mating holes in the base of the crate. Unfold the ramp onto the floor.

3.

Install the first side panel of the crate (with the large foam pad) as a guide
to help you position the pedestal on the base.

4.

The cable skirts around the pedestal base (4 in total) must be raised fully
before you drive the pedestal up the ramp onto the crate base. For each
skirt, loosen the thumbscrews, raise the skirt and tighten the thumbscrews.

5.

With the MCB controller in Remote, press and latch Standby/Charge, and
then press Run.

6.

Allow 30 seconds for the pedestal circuits to initialize.

7.

Switch the MCB controller to Local and Drive mode. Drive the pedestal to
the base of the ramp. Use Rotate mode to line up the pedestal with the
ramp. As shown in the photo on the previous page, the North side of the
pedestal goes up the ramp first.

8.

Carefully drive the pedestal up the center of the ramp. Note: Even with the
cable skirts raised, they may hang up on the bottom of the ramp and also at
the top. If this happens, have an assistant pull up slightly on the pedestal so
that the skirt will clear.

9.

When the pedestal is correctly positioned on the base of the crate, switch to
Rotate mode on the MCB controller and then switch to Remote. Push down
and latch all three Emergency STOP switches.

10. Remove the E-STOP bypass jumper plug.