9 modes of operation and field control wiring, Installation – AERCO BMK 3.0 LN Dual-Fuel Series Gas Fired Low NOx Boiler System User Manual

Page 17

Advertising
background image

INSTALLATION

2-7

For electrical power wiring diagrams, see the

AERCO Benchmark 3.0 Electrical Power Wiring

Guide, (GF-3060).

GND

NEU

L2

L3

L1

208 VAC, 3 PHASE

208 VAC, 3 Phase

GND

L2

L3

L1

460 VAC, 3 PHASE

460 VAC, 3 Phase

Figure 2-9

AC Terminal Block Configurations


2.9 MODES OF OPERATION AND FIELD

CONTROL WIRING

The Benchmark 3.0 Dual-Fuel Boiler is available

in several different modes of operation. While

each unit is factory configured and wired for its

intended mode, some additional field wiring may

be required to complete the installation. This

wiring is typically connected to the Input/Output

(I/O) Box located on the lower portion of the unit

front panel (Figure 2-10) behind the removable

front door.
To access the I/O Box terminal strips shown in

Figure 2-10, loosen the four cover screws and

remove the cover. All field wiring is installed

from the rear of the panel by routing the wires

through one of the four bushings provided.

TERMINAL

STRIPS

LOWER RIGHT CORNER

OF FRONT PANEL

Figure 2-10.

Input/Output (I/O) Box Location


Refer to the wiring diagram provided on the

cover of the I/O Box (Figure 2-11) when making

all wiring connections.
Brief descriptions of each mode of operation,

and their wiring requirements, are provided in

the following paragraphs. Additional information

concerning field wiring is provided in paragraphs

2.9.1 through 2.9.9. Refer to Chapter 5 for

detailed information on the available modes of

operation.

Advertising