AERCO Innovation (G-13-1854 and above) User Manual

Page 54

Advertising
background image

Innovation Water Heaters Installation, Operation & Maintenance Manual

CHAPTER 4 – INITIAL START-UP

Page 54 of

196

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

OMM-0078_0J

PRI: 11/22/2013

Phone: 800-526-0288

GF-128

Natural Gas Combustion Calibration - Continued

11.

Next, decrease the valve open position to 16% using the ▼ arrow key. Verify that the gas
pressure at the inlet of the SSOV is 8.0” to 11.0” W.C. Readjust the inlet gas pressure if
necessary.

12. Insert the combustion analyzer probe into the 1/8” port at the rear of the exhaust manifold.

Allow enough time for the combustion analyzer to settle.

13. Verify that the oxygen (O

2

)

level is within the range

shown below.

Also, ensure that the

carbon monoxide (CO), nitrogen oxide (NOx) and flame strength readings are within the
values shown.

Combustion Oxygen Level at 16% Valve Position

Oxygen %

± 0.5

Carbon

Monoxide

NOx

Flame

Strength

6.5 %

<50 ppm

<15 ppm

>2.0 µA

14. If the oxygen level is not within the required tolerance, the gas pressure on the downstream

side of the SSOV must be adjusted using the adjustment screw on the SSOV regulator
(Figure 4-4). Slowly rotate the gas pressure adjustment (approximately 1/4-turn
increments). Allow the combustion analyzer to stabilize following each adjustment.
Clockwise rotation reduces the oxygen level, while counterclockwise rotation increases the
oxygen level.

15. Once the oxygen level is within the required range listed in step 13, the gas pressure on the

downstream side of the SSOV should be within the appropriate range shown below for the
Innovation Model being tested.


INNOVATION MODEL

GAS PRESSURE RANGE

DOWNSTREAM OF SSOV

INN 1350

3.0” – 3.2” W.C.

INN1060

2.6” – 2.8” W.C.

INN800

1.5” – 1.7” W.C.

INN600

0.9” – 1.1” W.C.

16. Replace the brass cap on the SSOV gas pressure adjustment if it was previously removed.

17. Following combustion calibration at the 16% valve position, check the combustion readings

at each of the valve positions listed below and record the readings on the Start-Up &
Registration data sheets provided with the unit. During these checks, DO NOT attempt to
adjust the downstream gas pressure using the SSOV gas pressure adjustment screw.

NOTE

Based on the water heater load, it may not be possible to obtain data at all of
the points listed without encountering an Over-Temp condition.

18. Valve Positions to be checked:

• 20%,
• 30%,
• 40%,
• 50%,

• 60%,
• 80%,
• 100%

This completes the Natural Gas combustion calibration procedure.

Advertising