Installation, Field-supplied hardware – Carrier RTU OPEN 11-808-427-01 User Manual
Page 11

RTU Open
5
To install the RTU Open:
1
Mount the controller (page 6).
2
Wire the controller for power (page 7).
○
Using the rooftop equipment control power transformer (page 8).
○
Using an auxiliary control power transformer (page 8).
3
Set the controller's address (page 9).
4
Wire inputs and outputs (page 12).
5
Wire sensors to the controller (page 18).
Field-supplied hardware
An RTU Open retrofit installation may require the following field-supplied components:
•
wiring harness: Part #OPN-RTUHRN
•
transformer – 24 Vac, 20 VA minimum
•
wiring
Application-dependent components:
•
carbon dioxide sensors
•
damper/damper actuator
•
differential pressure switch
•
enthalpy switch
•
fan status switch
•
door switch
•
fan section door switch
•
relative humidity sensor
•
remote occupancy contact
•
smoke detector
•
temperature sensors
Installation