18

Table 7 (page 20) lists the correct orifice size to use at
different altitudes.

After changing the orifices, it is required that you measure
the gas input rate by clocking the gas meter and using
the local gas heating value. See Verifying and Adjusting
the Firing Rate section on page 19.

START UP & ADJUSTMENTS

Pre-Start Check List

Verify the unit is level and allows proper condensate

drainage.

Verify all clearance requirements are met and there is

free airflow to and from the outdoor coil.

Verify that the duct work is sealed to prevent air leakage.

Verify that the line voltage power leads are securely

connected and the unit is properly grounded.

Verify that the low voltage wires are securely connected

to the correct leads on the low voltage terminal strip.

Verify that the gas line service pressure does not exceed

10.0 inches WC (0.36 psig), and is not less than 4.5
inches WC (0.16 psig) for natural gas. For LP gas the
line service pressure must not exceed 14 inches WC
(0.51 psig) and must not be less than 11.0 inches WC
(0.40 psig).

Verify that the flame roll-out control is closed. If

necessary, press the red button to reset the control. DO
NOT
install a jumper wire across the control to defeat
its function. If the control reopens upon start-up, DO
NOT
reset the control without identifying and correcting
the fault condition which caused the control to trip.

Verify that the gas line has been purged and all

connections are leak tight.

Verify that all exterior panels are replaced and securely

fastened.

Verify that the outdoor fan turns freely.

Verify that the power supply branch circuit overcurrent

protection is sized properly.

Verify that the thermostat is wired correctly. The

thermostat function switch should be set to OFF and
the thermostat fan switch should be set to AUTO.

Start-Up Procedure

WARNING:

If this unit is equipped with crankcase heaters,
allow 24 hrs for heating of the refrigerant
compressor crankcase prior to start up and
anytime the power has been removed for more
than 12 hrs. Failure to comply may result in
damage or cause premature failure of the
system.

• Check all electrical wiring for loose connections and

tighten as required.

• Check unit for return air filters and condensate trap.

• Close all electrical disconnects to energize the system.

Air Circulation

Leave the thermostat system mode on OFF and set the
fan mode to ON. Blower will run continuously. Check the
air delivery at the supply registers and adjust register
openings for balanced air distribution. Examine ductwork
for leaks or obstruction if insufficient air is detected. Set
the thermostat fan mode to AUTO. The blower will stop
running.

Short Cycle Protection

1. With the system operating in cooling mode, note the

temperature setting of the thermostat and gradually raise
the set-point temperature until the unit de-energizes.

2. Immediately lower the set point temperature of the

thermostat to its original setting and verify that the
indoor blower is energized.

3. After approximately 5 minutes, verify the compressor

and fan energize and the temperature of the discharge
air is cooler than the room temperature. NOTE: This is
available only for the single phase models.

System Cooling Operation (2-Stage)

1. Set the thermostat’s system mode to COOL and the

fan mode to AUTO. Lower the thermostat temperature
setpoint one degree below room temperature and verify
the outdoor unit and blower energize on 1st stage cool.

2. Feel the air being circulated by the indoor blower and

verify that it is cooler than ambient temperature. Listen for
any unusual noises. If unusual sounds occur, determine
the source of the noise and correct as necessary.

3. After determining the system is operating properly, wait

1-2 minutes and then lower the thermostat temperature
set point an additional 3-4 degrees until the cooling
system moves into 2nd stage or high cool operating
mode. The compressor and indoor blower will increase
in speed.

4. Allow the cooling system to operate for several minutes

and then set the temperature selector above room
temperature. Verify the fan and compressor cycle off
with the thermostat. NOTE: The blower should also stop
in approximately 60 seconds, unless the fan switch is
set to the ON position.

System Heating (Heat Pump Mode)

1. Set the thermostat system mode to HEAT and the fan

mode to AUTO. Raise the thermostat temperature set
point one degree above room temperature and verify
the outdoor unit and blower energize on 1st stage heat.

2. Feel the air being circulated by the indoor blower and

verify that it is warmer than ambient temperature.

Listen for any unusual noises. If unusual sounds
occur, determine the source of the noise and correct
as necessary.

3. After determining the system is operating properly,

raise the thermostat temperature set point an additional
1-2 degrees until the system moves to 2nd stage heat
pump mode of operation. The compressor and blower
will increase in speed during 2nd stage cooling.