Tie Down Vector Dynamics Foundation System for Wind Zones lll User Manual

Page 16

Advertising
background image

D103

0

Tie Down Engineering

255 Villanova Drive SW

Atlanta, Georgia 30336

(404) 344-0000 • Fax (404) 349-0401

www.tiedown.com

Example of a Triple Section 32' x 72' Home

WIND ZONE I for Triple Section Homes

Using Vector Dynamics Foundation Systems

Soil Classifications: 2, 3, 4A & 4B

Soil Bearing Capacity: 1,000 PSF Minimum

Anchors Required*: None (*Marriage wall and sheer wall anchors may be required by home manufacturer.)

Home Length

Vector Systems Anchors Required

Longitudinal

Required

Per Side

System

1

(LSD)

0 to 48'

2 + 2 on Tag

0*

2 (4 Struts)

49' to 71'

3 + 2 on Tag

0*

2 (4 Struts)

72' to 84'

4 + 2 on Tag

0*

2 (4 Struts)

85' to 90'

5 + 2 on Tag

0*

2 (4 Struts)

NOTES:
* When a pier height at Vector locations exceeds 46”, an anchor must be used on the outside wall/beam at
that approximate location. Vector Systems should be spaced as symmetrical as possible along the length of
the home. Pier spacing must be consistent with home manufacturers instruction and/or state requirements.
Maximum allowable working load for metal strut: 3150 lbs.

1

One Longitudinal Vector System is made up of 2 struts, which can be used separately.

Vector Systems

LSD

LSD

LSD

LSD

Tag or Full Triple

16

Revised: 8/19/08

Advertising