Dunkirk Helix VLT Vertical Laser Tube, Wall Hung Modulating Condensing Boiler User Manual

Page 36

Advertising
background image

36

9.1 Fill Boiler With Water And Purge Air

NOTICE

To maintain boiler efficiency and prevent boiling

inside the heat exchanger, flush entire heating

system until clean.

• Flush heating system, including all heating zones.
• Fill boiler with potable water.
• Fill boiler and system piping with water (or

antifreeze-water solution, if used). See antifreeze

information page 13. Purge air from boiler using air

vent. Purge air from system piping.

• Inspect system piping and boiler connections. Repair

any leaks immediately.

• Activate all heating zones and calls for heat,

including CH calls and DHW calls (if available).

• Close manual gas shut off valve. Let system run for

30 minutes. When boiler goes into lockout, reset

boiler by pressing "Reset" button until boiler resets.

• Do not open gas shutoff valve until all air is purged

from system.

9.2 Fill Condensate Trap with Water

• Disconnect spring tension clip from condensate hose

barb. See figure 9-1.

• Disconnect tubing below from hose barb.
• Pour approximately 2 cups (473 ml) of water into

condensate drain.

• Reconnect tubing to hose barb with spring tension

clip. See figure 9-1.

FIGURE 9-1 Condensate Drain Assembly

NOTICE

IMPORTANT: Condensate trap must be manually

filled with water at initial start up.

2. Reconnect hose to hose

barb with spring tension clip

before starting boiler.

1. Disconnect spring tension

clip from hose barb and fill

Condensate trap with water.

9 - START UP PROCEDURE

Advertising