Installation – Glow-worm Clearly Heat Pumps - Standalone System User Manual

Page 19

Advertising
background image

0020096321_01 - 02/11 - Glow-worm

- 17 -

A - Case of a mono-zone installation :

•

Open the diff erent heating circuit air vent (on the pump and

the hydraulic module tank...).

1

Select Air venting on the

screen.

2

Select Vent heating circuit

on the screen.

•

Open the taps on the module hydraulic jig and the installation

domestic cold water inlet tap.

•

Fill the installation until the control unit shows 1.5 bar of

pressure.

•

Close the cold water inlet shutoff tap.

•

Vent each radiator until normal water fl ow then close the

venting valves.

•

Vent the hydraulic module tank.

•

Repeat the operation until all the radiators and the module

tank are vented.

3

Select Begin manual

venting on the screen.

The venting process is carried

out for 15 minutes. You

can simultaneously run the

venting of the HP circuit.

•

Check that the pressure

has not reduced (1.5

bar). If it has, repeat the

previous operations.

b

When venting is complete, close the diff erent heating

circuit air vent.

B - Case of a multi-zone installation :

The heating circuit can only be fi lled via the control unit if you

have chosen the multi-zone kit option. It is used to open the valves

of each zone.

1

Select Fill htg circuit

on the screen

The screen shows the

pressure measured in the

system.

•

Open the taps on the

module hydraulic jig and the

installation domestic cold

water inlet tap.

2

Select Begin fi lling

procedure from the screen.

3

The screen displays the

pressure measured in the

system and that installation

fi lling is in progress.

•

To stop fi lling press the button

.

•

Close the fi lling loop.

•

Vent each radiator until normal water fl ow then close the

venting valves.

•

Vent the hydraulic module tank.

•

Repeat the operation until all the radiators and the module

tank are vented.

•

Open the diff erent heating circuit air vent (on the pump and

the hydraulic module tank...).

3

Select Air venting on the

screen.

4

Select Vent heating circuit

on the screen.

5

Select Begin manual

venting on the screen.

The venting process is carried

out for 15 minutes. You

can simultaneously run the

venting of the HP circuit.

•

Check that the pressure

has not reduced (1.5

bar). If it has, repeat the

previous operations.

b

When venting is complete, close the diff erent heating

circuit air vent.

INSTALLATION

EN

Advertising