If any change in NPSH

A

is proposed, ensure these

margins are not significantly eroded. Refer to the
pump performance curve to determine exact
requirements particularly if flow has changed. If in
doubt please consult your nearest Flowserve office for
advice and details of the minimum allowable margin
for your application.

5.9.5 Pumped flow
Flow must not fall outside the minimum and maximum
continuous safe flow shown on the pump performance
curve and/or data sheet.

6 MAINTENANCE


6.1 General

It is the plant operator's responsibility to ensure

that all maintenance, inspection and assembly work is
carried out by authorized and qualified personnel who
have adequately familiarized themselves with the
subject matter by studying this manual in detail. (See
also section 1.6.2.)

Any work on the machine must be performed when it
is at a standstill. It is imperative that the procedure for
shutting down the machine is followed, as described in
section 5.8.

On completion of work all guards and safety devices
must be re-installed and made operative again.

Before restarting the machine, the relevant
instructions listed in section 5, Commissioning, start
up, operation and shut down

must be observed.


Oil and grease leaks may make the ground
slippery. Machine maintenance must always
begin and finish by cleaning the ground and the
exterior of the machine.

If platforms, stairs and guard rails are required for
maintenance, they must be placed for easy access to
areas where maintenance and inspection are to be
carried out. The positioning of these accessories
must not limit access or hinder the lifting of the part to
be serviced.

When air or compressed inert gas is used in the
maintenance process, the operator and anyone in the
vicinity must be careful and have the appropriate
protection.

Do not spray air or compressed inert gas on skin.

Do not direct an air or gas jet towards other people.


Never use air or compressed inert gas to clean
clothes.

Before working on the pump, take measures to
prevent an uncontrolled start. Put a warning board on
the starting device with the words:
"Machine under repair: do not start"

.


With electric drive equipment, lock the main switch
open and withdraw any fuses. Put a warning board on
the fuse box or main switch with the words:
"Machine under repair: do not connect".


Never clean equipment with inflammable solvents or
carbon tetrachloride. Protect yourself against toxic
fumes when using cleaning agents.

6.2 Maintenance schedule

It is recommended that a maintenance plan and

schedule is adopted, in line with these User
Instructions, to include the following:
a) Any auxiliary systems installed must be

monitored, if necessary, to ensure they function
correctly.

b) Gland packings must be adjusted correctly to give

visible leakage and concentric alignment of the
gland follower to prevent excessive temperature
of the packing or follower.

c) Check for any leaks from gaskets and seals. The

correct functioning of the shaft seal must be
checked regularly.

d) Check bearing lubricant level, and if the hours run

show a lubricant change is required.

e) Check that the duty condition is in the safe

operating range for the pump.

f) Check vibration, noise level and surface

temperature at the bearings to confirm satisfactory
operation.

g) Check dirt and dust is removed from areas around

close clearances, bearing housings and motors.

h) Check coupling alignment and re-align if

necessary.

Our specialist service personnel can help with
preventative maintenance records and provide
condition monitoring for temperature and vibration to
identify the onset of potential problems.

If any problems are found the following sequence of
actions should take place:
a) Refer to section 7, Faults; causes and remedies,

for fault diagnosis.

b) Ensure equipment complies with the

recommendations in this manual.

c) Contact Flowserve if the problem persists.