Tools & materials required – Greenheck Melink IH3 Installation User Manual
Page 3

Melink Corporation (513) 965-7300 www.melinkcorp.com
Tools & Materials Required
Materials Required
●
Suitable fasteners for mounting the System Controller and Variable Frequency Drive
(VFD)
▫ hollow cinder block (3/16” toggle bolts)
▫ concrete or filled cinder block (lead anchors 1/2” dia. with 1/4” x 1-14” lag screws)
▫ drywall (3/16” toggle bolts)
▫ plywood (#8 X 1-1/4” wood screws)
▫ metal back-plate (#8 X 1-1/4” sheet metal screws)
●
Conduit and wire for wiring the System Controller and VFDs
Tools Required
●
Drill and Drill Bits (Cobalt is best for stainless steel) - bit sizes: 1/8” & 1/4”
●
Hole Cutter or Punch for Stainless Steel with cutter sizes: 1-1/2” & 1-1/8”
●
Adjustable Pliers and Adjustable Wrench
●
Screwdrivers - Straight & Phillips, Large and Small
●
Wire Cutter and Wire Stripper
●
Measuring Tape and Level
●
Step Ladder
Note:
All high voltage wiring to be completed by trained service personnel. (Local code
may require a licensed electrician.)
3