C. Vertical Penetration Framing

Figure 6.3

Figure 6.4 Installing the Attic Shield

ATTIC ABOVE

A

PIPE

SLP

A

9 in. (229 mm)

A

A ceiling fi restop MUST be used between
fl oors and attics.

• Frame opening 9 in. x 9 in. (229 mm x 229

mm) whenever the vent penetrates a ceiling/
fl oor (see Figure 6.3).

• Frame the area with the same sized lumber

as used in ceiling/fl oor joist.

• The ceiling fi restop may be installed above or

below the ceiling joists when installed with a
attic insulation shield. It must be under joists
between fl oors that are not insulated. Refer
to Figure 6.4.

• Secure with three fasteners on each side.

WARNING! Risk of Fire! DO NOT pack insu-
lation around the vent. Insulation must be kept
back from the pipe to prevent overheating.

3 FASTENERS

PER SIDE

INSTALL ATTIC INSULATION SHIELDS

BEFORE OR AFTER INSTALLATION OF VENT SYSTEM

CEILING FIRESTOP

INSTALLED BELOW CEILING

CEILING FIRESTOP

INSTALLED ABOVE CEILING