Installation Guide ____________

;

Unpack and Place MD-1000LT

1. Compare the dishwasher and site utility connections.

2. Level the dishwasher by adjusting the bullet feet.

3. Raise the doors and check the door clearance to the ceiling.

4. Move the dishwasher to its permanent location.

Utility Connections - MD-1000LT

Power:

115VAC 15Amp circuit

Water supply:

3/4" NPT hot water supply (140°F/60°C minimum)
(35 psi/241 KPa static pressure) 7-10 psi/63-69Kpa flow pressure

Drain:

1-7/8" stainless steel, slip-fit hose connection
Max flow: 15 Us gal/min. (13.5 Imperial gal/min) 57liters/min.

Chemicals:

Detergent, rinse-aid, and sanitzer pumps are standard equipment.

Chemicals supplied by a chemical supplier

Chemical Dispensing Pumps - Factory Installed for MD-1000LT

All pumps use liquid chemicals

Detergent pump capacity =

350cc/min @ 108 RPM

Factory setting for detergent =

105cc in 18secs.

Rinse-aid pump capacity =

35cc/min @ 14RPM

Factory setting for rinse-aid

14cc in 23 sec.

Sanitizer pump capacity =

35cc/min @ 14RPM

Factory setting for Sanitizer=

14cc in 23 sec.

maintains 50PPM concentration of
5.25% sodium hypochlorite during
the final rinse cycle.

Note:
Installers must follow applicable sanitation, safety, plumbing, and electrical codes and
regulations; and work in accordance with best practices for dishwasher installation.