ASTAT-CD Plus Service Instructions

10

To replace the Protection Board.

NOTE: POWER MUST BE REMOVED

BEFORE SERVICING.

Step 14. Remove the cover and Logic Board/ Power

Supply Board assembly using steps 1 - 3, 9-10.

Step 15. Remove 6 wire connectors from the

Protection Board (Figure 11). Note the
locations of these terminals for reassembly.

6- point Terminal
Board

Protection
Board

Wire connectors

Figure 11. Remove push on wire connectors

Step 16. Disconnect the 4 leads from the two current

transformers and the 2 leads from the
thermostat to the 6 -point Terminal Board
(TB) (located at the top right edge of the
Protection Board)(Figure 10). Label these
leads to assure connections are the same to
the 6- point terminal board on the new
Protection Board.

Step 17. Loosen the 4 screws holding the Protection

Board to the housing. Remove the Protection
Board from the ASTAT-CD Plus.

Step 18. Reassemble the new Protection Board, CT

leads, thermostat leads, screws, gate wires and
ground wire, Logic and Power Supply Board
assembly, screws and ribbon connectors in the
reverse order of the above listed disassembly
(steps 12 and 6).

Step 19. Reassemble the plastic cover, connectors and

sheet metal covers using step 7.

To replace SCR modules

NOTE: POWER MUST BE REMOVED
BEFORE SERVICING.

SCR disassembly instructions - Size J

Current
transformers

SCR modules

Bus bars

Figure 12. SCR module, MOV and bus bar

location (Size J)

SCR disassembly instructions -
Sizes L and M

MOV

SCR modules

Bus bars

Connectors to
Protection Board

Figure 13. SCR module, MOV and bus bar

location (Sizes L and M)