Step 18. Label the 6 push-on wire connectors with the

numbers printed on the P.C. Board (U1, V1,
W1, U2, V2, W2). Remove 6 push-on wire
connectors from the Protection Board
(Figure 9). Note the location of these
terminals for reassembly.

Step 19. Label the 4 leads from the two current

transformers and the 2 leads from the
thermostats to assure connections are the
same to the 6-point Terminal Board on the
new Protection Board. Disconnect the 4 leads
from the two current transformers and the 2
leads from the thermostats to the 6-point
Terminal Board (Figure 8).

Step 20. Loosen the mounting screws holding the

Protection Board to the housing. Remove the
Protection Board from the ASTAT-CD Plus.

Reassembly

Step 21. Reassemble the new Protection Board, the

push-on wire connectors, the CT leads,
thermostat leads, screws, gate wires and
ground wire (if used), Logic and Power
Supply Board assembly, screws and ribbon
connectors in the reverse order of the above
listed disassembly (Steps 16-20).

Step 22. Reassemble the plastic cover, connectors and

sheet metal cover using steps 8-10.

To replace SCRs

NOTE: POWER MUST BE REMOVED
BEFORE SERVICING.

Step 23. Remove the front cover by removing the (4)

Phillips head screws (Figure 1).

Step 24. Phase 1 or 3 - Remove bus bars, the fan

assembly, the top ventilating cover and the
heat sink insulator cover. Remove the
thermostat wires, gate and cathode leads from
the SCRs, current transformer leads from the
C. T. (only on Phase 1) and other parts that
interfere with removal of the SCR/heatsink
assembly (Figure 10).

Phase 2 - Remove bus bars, the fan assembly,
the top ventilating cover and the heat sink

insulator covers from both phase 1 and Phase
3 heatsink assemblies. Remove (4) Allen
screws in the black plastic bottom housing
that holds the Control assembly to the
heatsink assembly and move the assembly to
the side. Remove the thermostat wires, gate
and cathode leads from the SCRs, current
transformer leads from the C. T.’s, and other
parts that interfere with removal of the
SCR/heatsink assembly (Figure 10).

Terminal

Blower

Circuit board

Heatsink

Board

transformers

assembly

insulating cover

Phase 1

Phase 2

Phase 3

Current

MOV

Bus bar support

Bus bar

transformers

bracket and

fan assembly

Figure 10. Parts locations insulating covers

Step 25. Remove the bolts on the ends of the heatsink

assembly that hold the H. S. assembly to the
housing insulators. Then slide the H. S.
assembly out the bottom of that ASTAT
housing. (Figure 11). Retain all parts and
hardware for reassembly.