9

Step 12. Reassemble the standoffs to the new Power

Supply Board. Reconnect the gate wires.
Reference Figure 8 for gate lead connections
for Size J, Figure 9 for Size K, or Figure 10 for
Sizes L and M.

Step 13. Reassemble the Logic Board, cover and

terminal connectors using Steps 6 - 7.

A PHASE

SCR

B PHASE

SCR

C PHASE

SCR

4 5 6 7

4 5 6 7

4 5 6 7

Y
Y

B

B

TB1

POWER BOARD - INVERTED

TB2

TB3

1 2 3 4

5 6 7 8

9 10 11 12

B = Blue(SCR-Cathode connection)
Y = Yellow(SCR-Gate connection)

A PHASE

SCR

B PHASE

SCR

C PHASE

SCR

4 5 6 7

4 5 6 7

4 5 6 7

Y
Y

B

B

TB1

POWER SUPPLY BOARD - SOLDERSIDE

TB2

TB3

1 2 3 4

5 6 7 8

9 10 11 12

B = Blue(SCR-Cathode connection)
Y = Yellow(SCR-Gate connection)

Figure 8. Gate lead connections (Size J)

Figure 10. Gate lead connections

(Sizes L and M)

SCR lead pairs are to be twisted to

reduce EMI (not shown in sketch).

A PHASE

SCR

B PHASE

SCR

C PHASE

SCR

4

5

6

7

4

5

6

7

4

5

6

7

Y
Y

B

B

TB1

POWER SUPPLY BOARD - SOLDERSIDE

TB2

TB3

1 2 3 4

5 6 7 8

9 10 11 12

B = Blue(SCR-Cathode connection)
Y = Yellow(SCR-Gate connection)

Figure 9. Gate lead connections (Size K)

Y = yellow wire (gate). B = blue wire (cathode)