Receiving, Handling and Storage

4

© 2011 General Electric All Rights Reserved

Figure 2-3 Placing forklift tines under shipping skid

Figure 2-4 Placement of rollers under shipping skid

NOTICE

If shipping skids are removed prior to final placement

of equipment, rollers may only be used to move the

equipment in a direction parallel to the front.

4. While carefully pushing the switchgear to its final site

position, the rollers that are freed from the rear of the

switchgear are then repositioned at the forward end.

This procedure should be continued until the

switchgear is in its final location. See Fig. 2-8.

5. When the switchgear is in its final position, remove all

lug bolts holding the shipping skids to the switchgear

line-up.

6. Insert the tines of the forklift at one end of the line-

up, raise slightly, and remove the loose rollers.

7. Lower the end of the gear carefully to the floor.

8. Raise the other end of the line-up slightly and

remove the remaining roller at that end.