SECTION 9. ENERGIZING THE SWITCHGEAR

BEFORE ENERGIZING

Before switchgear is energized, a thorough final check

should be made using the following checklist. Refer to Final

Steps to Be Taken Before Energizing Equipment (page 26)

for additional information.

• Breakers and other operating mechanisms exercised
• Electrical insulation resistance tested phase-to- phase

and phase-to-ground

• Relays, meters and instruments properly connected
• Electrically operated breakers and operating

mechanisms exercised

• Ground fault protection system tested
• Adjustable trips properly set
• Field wiring secured and free of live bus
• Grounding connections made
• All debris, scrap wire, etc. removed
• All covers installed, doors closed and latched

Uninterruptable Power Supply

Some Arc Vault stacks come equipped with a UPS device

located in the lower compartment. Refer to Figure 9-1.

This GE Digital Energy™ GT Series UPS units is sized

depending on the switchgears control voltage rating.

Start-up instructions are located on pg. 12-13 in the GT

series UPS user manual #5011319902.

The service life of the battery is from 3 to 6 years. It is

advised to regularly perform a battery test to ensure

failsafe operation. When the condition of the battery is

critical, a “Replace Battery” alarm will be activated. Have

the batteries replaced as soon as possible.

For more information call 903-640-7900.

POTENTIAL TRANSFORMER FUSE BLOCK FB1

Located in the controls compartment shown in Figure 3-3

on page 8 is the potential transformer fuse block labeled

FB1.

This fuse block is shipped in the OFF position, with a strip of

tape holding it in place. Remove the fuse block, rotate it 180

degrees and firmly reinsert it to seat it in the ON position.

WARNING

If the fuse block is not installed correctly then the Arc

Vault will not function nor provide protection. This

fuse block passes the arc event voltage and is critical

to the Arc Vault's firing decision.

ENERGIZING PROCEDURES

WARNING

Energizing switchgear for the first time is potentially

dangerous. Therefore, qualified electrical personnel

should be present when the equipment is energized. If

problems caused by damage or poor installation

practices have not been detected in the checkout

procedure described previously, serious damage can

result when power is turned on.

1. Device should be disconnected.

2. There should be no load on the switchgear when it is

energized.

3. Turn off all of the downstream loads, including those

such as motor control centers and other devices which

are remote from the switchgear.

4. The equipment should be energized in sequence by

starting at the source end of the system and working

toward the load end. In other words, energize the main

devices, then the feeder devices, and then the branch-

circuit devices.

5. Turn the devices on with a firm positive motion.